Large water tank installation at Army Bay.image: army-bayfile: army-bay-3.jpgslot: hero.army-bay-three-waters

Three Waters / PROJECT

Army Bay Three Waters.

Tank replacement, pipework and overflow connections, with demolition and reinstatement in a restricted-access environment.

Let's talk about your project
Location
Army Bay, Auckland
Delivery role
Main contractor
Period
2025
Disciplines
Three Waters / Project Delivery
Status
Completed

The project

Replacement of two tanks with the associated demolition, pipework interfaces, overflow connections and reinstatement.

The challenge

Restricted access made the construction sequence and interfaces important. Removal, replacement and reconnection needed to be considered as a complete civil scope.

Livic's scope

The supplied scope covers removal of the existing tanks, replacement tanks, plumbing or pipework interfaces, overflow connections and the surrounding reinstatement.

Key works

Tank replacement and associated civil interfaces. No tank dimensions, volumes or unverified client identity are published.

  • Demolition / removal of two existing tanks
  • Replacement tank installation interfaces
  • Plumbing and pipework coordination
  • Overflow connections
  • Reinstatement in restricted access

Construction approach

Restricted access shaped the lifting arrangements, temporary setup and sequence for tank replacement and connection works.

Quality

Quality checks focused on tank installation, pipework connections and overflow interfaces. No individual test result is stated.

Safety

Demolition, lifting, restricted access and live connections shaped site planning and sequencing.

Environment

The work included reinstatement around the tanks. No separate environmental outcome is claimed.

Stakeholders

As main contractor, Livic coordinated site access and specialist trade interfaces.

Outcome

Completed in 2025, the work replaced two tanks and included associated pipework interfaces, overflow connections and reinstatement.

ARMY BAY / BY THE NUMBERS

2

Tanks replaced

Project-specific quantities from the supplied brief. Approximate where noted.

NEXT PROJECT

East Coast Bays Bridge Club

START A CONVERSATION

HAVE A PROJECT?
LET'S BUILD IT.

If you have civil work coming up in Auckland, talk to us early.

Talk to Livic enquiries@liviccivil.co.nz027 406 2789